The Irish infrastructure build map: what is funded, what is approved, and what is actually being built
We track Ireland's infrastructure pipeline the same way we track the global one, because we cannot resource programmes we have not mapped. Ireland has committed EUR 275.4 billion to 2035 and rewritten how the work gets approved. This is the current edition: what is funded, what has cleared planning, what is on site, and why the binding constraint is no longer money.
Listen to this article
Audio · Jack, ROCWAN research
Listen to the overview – with Jack
The short version of the whole map in one voice: what is funded, what has cleared planning, the much shorter list of what is on site, and why it is a workforce problem first. About a minute.
Download the audio Keeps playing with the screen locked.
Audio · Jack and Sarah, in discussion
The build map – Jack and Sarah in discussion
Jack and Sarah work through the whole article: the EUR 275.4 billion and why it does not sum, the nine designated projects, the risk-appetite statement, the rail build, the delivery gap, the slip record, and the eighty-thousand-worker question. About twelve minutes.
Download the audio Keeps playing with the screen locked.
The short version
- Ireland has committed EUR 275.4 billion across 2026 to 2035, its third and biggest plan in eight years, and the July 2026 mid-year report put total five-year Exchequer capital at EUR 106.5 billion, EUR 4.1 billion above the amounts so far allocated to departments.
- On 24 July 2026 nine projects were placed at the top of the statutory queue, and on 8 July the State published a risk appetite statement, a formal statement of how much delivery risk the State will now accept, that moves spending earlier, before the approvals are certain.
- Ireland has more people in construction but is building less of the big engineering work. Employment across construction rose 11.7 per cent over the year to early 2026, while the volume of civil-engineering work put in place, the roads, water and rail slice, fell 15.5 per cent in the same quarter, and eased to a 4.4 per cent fall in the second, as large jobs finished before the next broke ground.
- Ireland's fiscal watchdog put the gap at almost 80,000 extra construction workers if productivity stays flat, or under 20,000 if it improves.
Where the work is going
Start with the island. Every major programme in the pipeline is pinned where it will be built, and the fills tell the truth at a glance: most of the map is hollow or dashed. The money is committed almost everywhere. The crews are on the ground in very few places.
Greater Dublin: 1 MetroLink 2 Dublin Airport 3 DART+ programme 4 BusConnects Dublin 5 Greater Dublin Drainage 6 Ringsend upgrade 7 Children's hospital 8 Intel Leixlip
Swipe the map sideways on a phone to see the whole island.
Transport
- MetroLink designated approved or in procurement EUR 7.9 billion of main civils tenders live, plus about EUR 1.9 billion of enabling-works notices; bidders not yet shortlisted; still to clear its next Government approval gate, the decision to proceed to construction tenders, expected autumn 2026; 7,200 to 9,100 direct construction jobs a year once it builds.
- Dublin Airport in planning The passenger cap law changed on 16 July 2026, but the EUR 2.9 billion infrastructure application that would physically serve 40 million passengers has sat undecided since December 2023.
- DART+ programme approved or in procurement Three of four projects approved; early works from 2026; DART+ South West construction has slipped about four years to 2030 plus.
- BusConnects Dublin on site now The bus-priority build has started: the first core corridor on site since September 2025, a second awarded December 2025, a third out to tender.
- N5 Ballaghaderreen to Scramoge on site now The counter-example: the first section opened in March 2026 roughly nineteen months ahead of programme.
- Galway City Ring Road designated in planning Approved 2021, quashed 2023, re-approved April 2026, facing four fresh judicial review applications listed for November 2026. Designated while under challenge.
- Adare Bypass on site now EUR 150 million, the one immovable deadline in the pipeline: open by June 2027, ahead of the Ryder Cup at Adare Manor. The critical-path bridge girders were placed by August 2026.
- Cork Area Commuter Rail designated on site now Twin-tracking on schedule for the end of 2026; the signalling element has slipped a year into 2027.
- M28 Cork to Ringaskiddy on site now EUR 456 million; on site since 2025; completion summer 2028, driven by the port move to deep water.
Water
- Greater Dublin Drainage designated approved or in procurement EUR 1.3 billion; a judicial review settled in December 2025, procurement opened February 2026, fourteen years after the project was announced; main construction 2027 to 2032.
- Ringsend upgrade complete EUR 550 million upgrade completed February 2026. The one big Dublin water scheme that finished, and the reason Greater Dublin Drainage is next.
- Water Supply Project, Eastern and Midlands designated in planning EUR 4.6 billion to EUR 5.9 billion; Ireland’s largest-ever water project, whose planning application ran to more than 30,000 pages; in July 2026 the commission moved its decision out by a full year.
- Limerick (Bunlicky) wastewater designated in planning Limerick wastewater upgrade and bioresource centre, one of the nine designated projects.
Energy and grid
- Letterkenny 110 kV designated in planning Letterkenny 110 kV redevelopment, one of the nine designated projects of 24 July 2026.
- Moneypoint 400 kV designated in planning Moneypoint 400 kV series capacitor, designated 24 July 2026; its planning appeal has no decision timeline.
- Shannon Foynes port in planning Maritime Area Consent granted July 2026; built for floating wind after 2030, so it adds nothing to the 2030 target.
- Cork port, Ringaskiddy on site now The furthest-advanced offshore wind port in the State: first berth due 2026, full build-out into 2027.
- Celtic Interconnector on site now 700 MW to France; about EUR 2 billion against EUR 930 million estimated in 2011; delivery has slipped twice to late 2028, and the grid operator names the delay as a cause of tight supply.
- Greenlink Interconnector complete 500 MW to Wales, in commercial operation since January 2025. It doubled the State’s interconnection.
- Rosslare offshore hub in planning EUR 220 million offshore wind hub; planning lodged December 2025, no decision yet.
- North-South Interconnector designated approved or in procurement Fully approved in both jurisdictions for years and still not built in the Republic; now designated, with completion listed for 2031.
- Oriel Wind Park in planning 375 MW off Louth; the only offshore case with a live statutory decision date, 21 September 2026.
- North Irish Sea Array in planning 500 MW; decision twenty months past its statutory date.
- Dublin Array in planning 824 MW; further-information response due August 2026.
- Codling Wind Park in planning 1,300 MW, the largest of the phase-one projects; still awaiting a decision.
- Arklow Bank 2 in planning 800 MW; awaiting a decision, and without a route to market after missing the first auction.
- Tonn Nua approved or in procurement 900 MW off Waterford, auctioned December 2025 at EUR 98.719 per megawatt hour; operation targeted for the mid-2030s.
Health
- Children's hospital on site now A budget first put at about EUR 650 to 800 million in 2014, about EUR 2.24 billion now; still not handed over as at August 2026.
Private capital, same labour pool
- Intel Leixlip on site now Private capital in the same labour pool: the EUR 17 billion Fab 34 programme, with a further EUR 5 billion announced in July 2026.
- Eli Lilly Limerick on site now Private capital in the same labour pool: a USD 2 billion campus at Raheen, with construction employment reported over 1,200.
30 programmes placed at their real locations; 9 of the pins carry the designation ring. Northern Ireland is drawn neutral because the National Development Plan stops at the border. Offshore markers sit at indicative positions in their array areas, and the two route lines are indicative alignments, not surveyed ones. County boundaries and motorways are drawn for orientation only, without names. Outlines and county boundaries are Natural Earth, public domain; motorway alignments contain information from OpenStreetMap, © OpenStreetMap contributors, ODbL.
Two things the map cannot show are stories in their own right. Offshore, the first-round wind projects are drawn dashed because not one of them holds planning permission: one, Sceirde Rocks, was withdrawn outright in December 2025 after its developer wrote off about EUR 50 million, and the rest are still at the planning commission, with the first decision, on Oriel, due by late September 2026. Industry has already conceded the five-gigawatt-by-2030 offshore target will be missed. And around Dublin, no new data centre pin can appear at all: the grid operator declared the greater Dublin region fully constrained in May 2026, with no end date, while data centres already took 22 per cent of the State's metered electricity in 2024 and are heading for close to a third by 2030.
The money is not the problem
Ireland has rewritten its national plan twice since 2018, upward both times. The current one commits EUR 275.4 billion over 2026 to 2035: EUR 202.4 billion Exchequer, EUR 63 billion non-Exchequer and EUR 10 billion of equity in State companies. The five-year department ceilings were set at EUR 102.4 billion, and the Mid-Year Expenditure Report of 30 July 2026 put total five-year Exchequer capital at EUR 106.5 billion, EUR 4.1 billion above the amounts so far allocated to departments. About EUR 17 billion was invested in 2025 and EUR 19 billion is projected for 2026, over 5 per cent of GNI*, the measure of the Irish economy with the multinational distortions stripped out.
- 2018Launched February 2018 as the first ten-year plan.
- 2021Held investment at about 5 per cent of GNI*, and flagged construction capacity as a key delivery risk in its own text.
- 2025Published 22 July 2025. Twelve months later the Mid-Year Expenditure Report put total five-year Exchequer capital at EUR 106.5bn, EUR 4.1bn above the amounts so far allocated to departments.
Each envelope is the whole-plan public investment figure at publication, Exchequer plus non-Exchequer, and each plan covers its own ten-year window, so the bars compare the scale of ambition rather than like-for-like annual spend. Capital spending is planned to average 5.2 per cent of GNI* across 2026 to 2030.
One correction, because the wrong number is everywhere. EUR 112 billion appears nowhere in the plan. It is the EUR 102.4 billion of ceilings plus EUR 10 billion of equity, added together by somebody else. And one piece of history worth knowing: the 2021 plan flagged construction capacity as a key delivery risk in its own text. Five years on, that is the story.
The two documents most of the market still quotes are out of date. The plan that ran to 2030 was replaced on 22 July 2025, and Prospects 2024/2025, still the procurement calendar in most people's heads, has no successor edition: sectoral investment plans replaced it in late 2025. The live list is the Investment Projects and Programmes Tracker, over 500 projects and 146 programmes above EUR 20 million at the end of 2024, against over 340 a year earlier.
Where the money sits
The sectoral plans set the shape, and the largest single network programme is in none of them, because a regulator sets it. The CRU's Price Review 6 determination of 16 December 2025 allows EUR 13.8 billion at baseline and up to EUR 18.9 billion across EirGrid and ESB Networks, and it funds the connection of 300,000 homes. That matches the 300,000-home housing target: the grid plan and the housing plan stand or fall on the same assumption.
Housing almost EUR 25bn Transport EUR 24.3bn Electricity networks EUR 13.8bn Water EUR 12.2bn Health EUR 9.25bn Education EUR 7.55bn
The same five-year sectoral envelopes as Figure four, redrawn as area rather than length: sectoral investment plans of November and December 2025 and the NDP Review Table 6, except electricity networks, which is the CRU Price Review 6 baseline allowance (its fully funded high case, to EUR 18.9bn, is not shown here). Housing is the almost EUR 25bn of NDP housing capital in the December 2025 housing plan. Transport's EUR 24.3bn is drawn as one block: within it, about EUR 10.1bn is public transport including rail and EUR 9.7bn is roads, with MetroLink adding roughly EUR 2bn more, a breakdown that does not itself sum to the sector total, so it is not sliced out of the box. Bases differ across sectors, so read the blocks as scale, not as one clean total.
- Housing almost EUR 25bn Almost EUR 20bn of it is social and affordable delivery, and every unit of it queues behind water and grid connections.
- Transport EUR 24.3bn About EUR 10.1bn public transport and EUR 9.7bn roads; MetroLink adds EUR 2bn more from the climate fund.
- Electricity networks set by the regulator EUR 13.8bn to EUR 18.9bn Price Review 6: an 80 per cent increase on the last period, funding the connection of 300,000 homes.
- Water EUR 12.2bn The gate on housing: serviceable capacity is about 35,000 new homes a year against a 50,000 target.
- Health EUR 9.25bn The children’s hospital has first call; the elective hospitals promised for 2025 to 2027 have not started.
- Education EUR 7.55bn Schools and youth. The bundled schools programmes are among the few delivering broadly to plan.
Five-year envelopes from the sectoral investment plans of November and December 2025 and the NDP Review Table 6, except the electricity networks bar, which is the CRU Price Review 6 allowance for EirGrid and ESB Networks with the paler extension showing its fully-funded high case. Housing is the almost EUR 25bn of NDP housing capital in the December 2025 housing plan. Bases differ, so read the bars as scale, not as one clean total.
EirGrid's own strategy makes the resourcing point for us: the grid operator plans to grow from 1,500 to over 2,000 people to deliver 381 transmission projects. A State body stating it must grow by a third to deliver its programme is the thesis of this article in miniature.
Nine projects went to the top of the queue
On 24 July 2026 the Government designated its first nine projects as critical infrastructure under the Critical Infrastructure Act 2026. They are the pins with the cyan ring on the map above.
- Transport: MetroLink, Cork Area Commuter Rail, Galway City Ring Road.
- Water: the Water Supply Project for the Eastern and Midlands Region, Greater Dublin Drainage, and the Limerick (Bunlicky) wastewater upgrade.
- Energy: the North South 400 kV Interconnector, the Moneypoint 400 kV Series Capacitor and the Letterkenny 110 kV Redevelopment.
Designation obliges every public body to prioritise these projects above any other and to run approval processes concurrently where possible, rather than in sequence. More orders follow through the year. It lands on a planning system that has itself been rebuilt mid-flight: An Coimisiun Pleanala replaced An Bord Pleanala on 18 June 2025, the new judicial review rules commenced on 1 August 2025, and the phased commencement of the Planning and Development Act 2024 has continued into 2026.
Two weeks earlier, on 8 July 2026, came the least covered item in the pipeline and the one that changes most about how a programme is run: the State's first risk appetite statement. Minister Chambers put the problem plainly: a small wastewater treatment project in Ireland takes seven to ten years, four to five years longer than elsewhere in the EU. Delivery bodies may now fund design before approval in principle, write procurement documents before the approvals land, buy land ahead of certainty and forward purchase critical materials. Every designated project must hold its own project-level risk appetite statement.
Every one of those moves spends money earlier against less certainty. Raising risk appetite without raising risk control capability is not acceleration, it is exposure.
Rail takes the largest single share of the transport money
No other mode takes as much of the transport plan as rail, and it is spread the length of the island, so it is easy to miss how much of the plan it adds up to. Put together it is where the bulk of the roughly EUR 10.1 billion of public-transport money goes, and it is the clearest case of the pattern in this piece: the permissions are landing and the money is committed, but almost nothing is yet being dug.
MetroLink, Dublin's underground metro, finally cleared its biggest legal hurdle: An Coimisiun Pleanala granted its Railway Order, the legal permission to build, on 2 October 2025, and it became operative on 12 January 2026. The building tenders are out, with a combined ceiling of EUR 7.9 billion before VAT for the two main civil-works packages, but the scheme's next Government approval gate, the decision to proceed to construction tenders, is still ahead, expected in autumn 2026. The cost is the open question. The only official figure, EUR 9.5 billion, dates from 2021; the revised estimate has not been published, and in July 2026 senior Government figures were reported to expect somewhere between EUR 15 billion and EUR 19 billion. On the current plan the first passengers are not carried before 2035.
DART+ is the programme electrifying and extending Dublin's commuter rail, and it splits three ways. DART+ West has its permission and begins enabling works and land purchase in 2026. DART+ Coastal North, out to Drogheda, is approved and has EUR 93 million of Shared Island funding to bring parts of it forward. DART+ South West is approved on paper but its construction has slipped to 2030 or later. The trains are on order, 285 carriages worth about EUR 670 million from Alstom, but the first battery-electric services have slipped from 2026 into 2027. Separately, a EUR 698 million order for eight new Enterprise trains for the Dublin to Belfast line was signed on 7 May 2026, for service from 2030.
Cork Area Commuter Rail is the rail scheme furthest along on the ground. Its new through-platform at Kent Station opened in April 2025, the double-tracking out to Midleton is due to finish in 2026, and the programme was named critical infrastructure on 24 July 2026. Eight new stations and full electrification of the Cork network follow in a second phase from 2028. In Dublin the Luas Finglas tram extension is cleared and buying land, its land notices issued on 4 August 2026, a roughly EUR 600 million line about to move into construction; a far larger Luas for Cork, put at EUR 2 billion to EUR 3 billion, is still only choosing its route. BusConnects, the bus-priority build, is already happening: the first Dublin corridor has been on site since September 2025, with further corridors contracted and out to tender.
Two long-closed lines are also reopening. The 42-kilometre Limerick to Foynes freight line has been relaid and is due to carry its first trains from October 2026, and the Western Rail Corridor between Athenry and Claremorris is funded to be delivered by 2030. A new line to Navan is further off, after 2030. For a firm that resources programmes this is the map that matters most: every one of these is a separate client and a separate delivery team, and they are bidding for the same signalling engineers, planners and cost managers at the same time.
Funded is not delivered
Ireland delivered its capital budget to within about one per cent of profile, the spending schedule the Government set for itself, in each of the last two full years. The Fiscal Monitor of 6 August 2026 records the State's own capital budget at EUR 7.6 billion to end-July, EUR 0.9 billion or 10.7 per cent below profile, in the best funded year in the history of the State. And in the first quarter of the year, construction's workforce grew while its output shrank.
Capital spend against profile
Gross voted capital against the published profile. Seven months is not a year and capital is back loaded, so the full-year gap will likely be smaller. The trend across the three periods is the point.
More people in, less output out
Not a price story: tender inflation across 2025 was 2.5 per cent, the lowest since 2020. An output fall partly reflects big jobs finishing before the next wave starts, which is exactly what a pipeline stuck between approval and construction looks like. The fall eased to 4.4 per cent year on year in the second quarter.
Set beside those two charts, without comment, the same Government's Mid-Year Expenditure Report of 30 July 2026: every Accelerating Infrastructure action due by the end of the first quarter is complete and the rest are on track.
The record: announcement to delivery
The pipeline's history is public and specific, and it is why the stage of a scheme matters more than its headline figure. Dublin has been planning a metro since 2000. The children's hospital was first put at about EUR 650 to 800 million for completion in 2020 and stands at about EUR 2.24 billion, with 3,165 contractor claims worth EUR 819 million adjudicated as at May 2026.
Announced Completion first promised Finished Still a forecast
For further balance: the N5 Ballaghaderreen to Scramoge road opened its first section in March 2026, roughly nineteen months ahead of programme, and the National Train Control Centre has moved from EUR 148 million to a forecast EUR 175 million to EUR 205 million with handover in November 2028.
MetroLink shows how far the stage of a scheme can lag its funding. After a quarter of a century in planning it only won its Railway Order, the legal permission to build, in October 2025; it has still to clear its next Government approval gate, the decision to proceed to construction tenders, expected in autumn 2026, and it will not carry a passenger before 2035. Its cost has drifted with it: the only official figure is the EUR 9.5 billion set in 2021, while the unpublished 2026 revision was reported in July to run as high as EUR 15 billion to EUR 19 billion, before a single tunnel is bored.
Water carries the same lesson with a live consequence: Uisce Eireann can service about 35,000 new homes a year against a 50,000 target, Greater Dublin Drainage will not operate before 2031 or 2032, and the Shannon abstraction scheme, Ireland's largest-ever water project, whose planning application ran to more than 30,000 pages, had its decision deadline moved out by a full year in July 2026. Ireland spent the summer of 2026 under a hosepipe ban, still in force in thirteen counties.
Eighty thousand, or twenty
The arithmetic that carries this piece is not ours. In Working Paper 23 of October 2024 the Irish Fiscal Advisory Council estimated that almost 80,000 additional construction workers would be needed to address Ireland's infrastructure deficits, a 47 per cent increase on current levels, and fewer than 20,000 if productivity improved. Government adopted that arithmetic into its Accelerating Infrastructure Report of December 2025, which puts Irish construction productivity about 30 per cent below the OECD average.
The State named the skill: Construction Planner and Scheduler was added to Ireland's Critical Skills Occupations List, in an update aimed at supporting delivery of the National Development Plan. Project controls scarcity is now on the State's own skills list, not argued.
The CITB expects UK construction to need 41,200 extra workers a year to 2030, about 206,000 in all, or 1.6 per cent of its workforce annually. Ireland's requirement is equivalent to a 47 per cent uplift on its whole base, and both markets recruit from the same pool.
The arithmetic is the Irish Fiscal Advisory Council's, from Working Paper 23 of October 2024, and the Government adopted it into its Accelerating Infrastructure Report in December 2025. It is the State's own number, not an industry claim.
The difference between the two columns is productivity, which is delivery capability, which is people who know how to run a programme. In May 2026 the State named the skill, adding Construction Planner and Scheduler to the Critical Skills Occupations List to support delivery of the National Development Plan.
What we do with it
We keep this map for the same reason we keep the global one: it decides where we build our resource pool and which programmes we are ready for before the call comes. In Ireland the useful signal is not the euro total, it is the gate. A scheme clearing its pre-tender approval (Gate 2) or opening pre-qualification, the first stage of a tender competition, tells us when project-controls and commercial demand lands, months before any award.
When a designated project stands up its own risk appetite statement, someone has to write the cost report that survives scrutiny of it. We would rather know who that is before the client asks. The private pins on the map are the other half of that call: the same pool of professionals is being bid for by Intel's Leixlip campus and Eli Lilly's Limerick build at the same time as the State's entire pipeline, and the United Kingdom, our secondary market, recruits from it too, needing 41,200 extra workers a year to 2030 against a NISTA pipeline of 734 projects worth GBP 718 billion.
Method and source
Drawn from ROCWAN research compiled on 24 August 2026 and re-validated on 28 August 2026, the cut-off for every figure above. Primary sources were preferred throughout, among them gov.ie, the CRU, the CSO, EirGrid, Uisce Eireann, Iarnrod Eireann, the NTA, TII, the Irish Fiscal Advisory Council and the primary texts of all three National Development Plans, with national press used for recency and traced back wherever possible. The full source list, each item dated, is in the references panel below. Map outlines are Natural Earth, public domain; pins sit at real locations, with offshore arrays and route lines drawn indicatively.
Three figures are handled deliberately. EUR 112 billion is not the NDP 2026 to 2030 figure: it is the EUR 102.4 billion of five-year ceilings plus EUR 10 billion of equity, added together elsewhere. The Shannon water scheme is the EUR 4.6 billion to EUR 5.9 billion range Uisce Eireann itself lodged, not a single printed upper bound. And MetroLink's only official cost is the EUR 9.5 billion set in 2021; its 2026 revision has not been published, so the higher figures in circulation, reported in July 2026 as EUR 15 billion to EUR 19 billion, are given as reported expectations of Government, not as an official estimate.
No total Irish construction headcount appears above because only the year-on-year change is published, and no quantity-surveyor-specific shortage figure appears because none has been verified. The offshore wind positions are the planning record as at 28 August 2026: of the first auction's projects one, Sceirde Rocks, was withdrawn in December 2025, and none of the rest holds planning consent.
References and sourcesHere are all the sources: every figure above traced to a dated original you can open and check
Sources verified as at 28 August 2026. Each entry links to the original document, and the date shown is that source’s own publication date. Where a figure was announced by a government body or by the company making a private investment, that original is listed first, ahead of any news coverage that later repeated it.
Official and primary sources
- Government of Ireland (gov.ie): National Development Plan 2026-2035, under Project Ireland 2040 (EUR 275.4bn)The EUR 275.4bn NDP total and its composition
- Government of Ireland (DPER): Government increases risk appetite to accelerate delivery of critical infrastructure projects (the Infrastructure Risk Appetite Statement)The risk appetite statement of 8 July 2026
- Government of Ireland (Dept of Transport): Cabinet approval for the EUR 24.3bn Transport Sectoral Investment Plan 2026-2030
- Government of Ireland (Dept of Transport): Rail Project Prioritisation Strategy
- An Coimisiún Pleanála: Establishment notice (replacing An Bord Pleanála)
- MetroLink / Transport Infrastructure Ireland: MetroLink Railway Order (granted 2 Oct 2025 by An Coimisiún Pleanála; operative 12 Jan 2026)
- Iarnród Éireann (DART+): DART+ West project (Railway Order, enabling works and contract timeline)
- An Coimisiún Pleanála: DART+ Coastal North (Dublin to Drogheda) Railway Order case
- Iarnród Éireann: Next phase of Cork Area Commuter Rail announced
- National Transport Authority: Luas Finglas Railway Order granted by An Coimisiún Pleanála
- National Transport Authority: First BusConnects Dublin core bus corridor awarded to GMC
- Transport Infrastructure Ireland: First section of the N5 Ballaghaderreen-Scramoge road opened
- Limerick City & County Council: Adare Bypass contracts signed as works advance
- M28 project office (TII / BAM): M28 Cork-Ringaskiddy construction progress update
- An Coimisiún Pleanála: N6 Galway City Ring Road case (approved with modifications)
- Uisce Éireann: Settlement of the Greater Dublin Drainage judicial review, project can proceed (EUR 1.3bn)
- Uisce Éireann: Procurement launched for Greater Dublin Drainage and the Water Supply Project
- EirGrid: EirGrid launches its new five-year strategy (EUR 18.9bn grid investment)
- EirGrid: North-South Interconnector project (consent, works and October 2031 completion)
- Government of Ireland (DCEE): State's second offshore wind auction result (Tonn Nua, 900MW)
- Commission for Regulation of Utilities: Price Review 6 final determination: record investment in the electricity grid and network (EUR 13.8bn baseline, up to EUR 18.9bn)The PR6 allowance and the 300,000 home connections
- Commission for Regulation of Utilities: New electricity connection policy for data centres
- Government of Ireland (Taoiseach): Delivering Homes, Building Communities 2025-2030
- Central Statistics Office: Labour Force Survey Q1 2026 (construction employment up 11.7%)
- Irish Fiscal Advisory Council: Working Paper 23: Ireland's Infrastructure Demands (almost 80,000 extra workers, or under 20,000 with better productivity)The 80,000 / 47 per cent / under-20,000 workforce arithmetic
- Government of Ireland (Dept of Culture, Communications and Sport): National Broadband Plan passes 500,000 premises
Reporting and analysis
- The Irish Times: MetroLink could cost up to EUR 19bn, senior Government figures believe (TII revision unpublished)
- RTÉ: MetroLink main civil-works tenders launched (EUR 7.9bn ceiling)
- RTÉ: Government fast-tracks nine critical infrastructure projects
- RailBusinessDaily: Almost EUR 230m Shared Island funding for all-island rail (DART+, Enterprise, track renewal)
- RailwayPro (reporting Alstom): 285 Alstom X'trapolis carriages (~EUR 670m); battery-electric entry slips to 2027
- RTÉ (reporting Iarnród Éireann / Stadler): EUR 698m Stadler contract for the new Dublin-Belfast Enterprise fleet
- Railway Gazette International: First new Cork commuter-rail stations targeted for 2028-29
- The Irish Times: Luas Finglas can proceed after High Court cases resolved
- New Civil Engineer: Sisk completes 42km track-laying for the Limerick-Foynes freight line
- Connaught Telegraph: Western Rail Corridor secured in the new transport sectoral plan
- The Irish Times: N6 Galway City Ring Road granted approval, then faces judicial review
- The Irish Times: Celtic Interconnector could cost EUR 2bn due to delays
- RTÉ: Decision on Shannon water-extraction project delayed to before July 2027
- RTÉ (reporting developer Corio): Plans withdrawn for the EUR 1.4bn Sceirde Rocks offshore wind farm
- The Irish Times (reporting Wind Energy Ireland): Planning bottleneck means Ireland will miss its 2030 offshore wind target
- RTÉ (reporting the CSO): New dwelling completions 2025: 36,284 (below the 41,000 target)
- RTÉ: National Children's Hospital cost ~EUR 2.24bn (latest official estimate)
- TheJournal.ie (reporting the ESRI): Ireland needs about 80,000 more workers for housing and infrastructure targets
- Mason Hayes & Curran: Ireland's infrastructure pipeline expands under NDP 2025 (analysis of the NDP breakdown)
The teams have to exist before the concrete does